Campus Oulu, Kaapelitie 4 (Rusko)

Data centre project, municipality: Oulu. Stage: under construction. Operator: Glesys / Trevian. Announced power: 300 MW. No municipal decisions found yet.

Status

Under construction (7/8)

Participation

Figures

Power
300 MW · announced
IT load
8 MW · announced
Area
6 ha · announced

Municipal decision trail · 0

No decisions related to this project were found in the municipality’s documents.

Municipal decisions do not cover state permits or private land deals. A project at the prospecting stage may not have reached municipal decision-making yet.

Operator

Other projects in this municipality

Oulu — All data and other projects in this municipality

Project data: Datakeskushankkeiden kansallinen rekisteri (datakeskusrekisteri.vercel.app), CC BY 4.0. Modified: combined with municipal decisions. Retrieved .