Hyperco Kouvola-Koria, Fin Holdco 1

Data centre project, municipality: Kouvola. Stage: under construction. Announced power: 64 MW. Latest municipal decision: 14 August 2024.

Status

Under construction (7/8)

Figures

Power
64 MW · announced
IT load
64 MW · announced
Area
13 ha · announced
Generators
33 kpl · announced

Municipal decision trail · 1

  1. · Kouvolan teknisen lautakunnan lupajaosto hyväksyi Korian datakeskuksen rakennusluvan noin 28 000 neliön datakeskuksen rakentamiselle Hiivurin alueelle; rakennuttajana Hyperco oy. · Kouvolan kaupunki · Permit

Operator

Other projects in this municipality

Kouvola — All data and other projects in this municipality

Project data: Datakeskushankkeiden kansallinen rekisteri (datakeskusrekisteri.vercel.app), CC BY 4.0. Modified: combined with municipal decisions. Retrieved .