Hyperco Pyhäjoki, Keskikylä

Data centre project, municipality: Pyhäjoki. Stage: under construction. Announced power: 369 MW. No municipal decisions found yet.

Status

Under construction (7/8)

Figures

Power
369 MW · announced
IT load
284 MW · announced
Area
240 ha · announced
Electricity use
3.2 TWh/a · announced
Generator fuel power
921 MW · announced
Generators
116 kpl · announced

Municipal decision trail · 1

  1. · Lupa- ja valvontavirasto antoi 17.6.2026 YVA-lain 23 §:n mukaisen perustellun päätelmän Hyperco Intelligence Oy:n Pyhäjoen datakeskuksen ympäristövaikutusten arviointiselostuksesta (LVV-U/53982/2026). · Lupa- ja valvontavirasto · State authority · Statement

Operator

Plan

Keskikylän teollisuusalueen asemakaava · Block: 900, 901

Other projects in this municipality

Pyhäjoki — All data and other projects in this municipality

Project data: Datakeskushankkeiden kansallinen rekisteri (datakeskusrekisteri.vercel.app), CC BY 4.0. Modified: combined with municipal decisions. Retrieved .