Scale42 Liperi

Data centre project, municipality: Liperi. Stage: prospecting. Operator: Scale42. Announced power: 60 MW. Latest municipal decision: 1 July 2026.

Status

Prospecting (1/8)

Figures

Power
60 MW · announced
IT load
60 MW · announced
Area
8.8 ha · announced

Municipal decision trail · 1

  1. · Vuokrasopimus ja esikauppakirja Scale42:lle Välikankaan ~9 ha datakeskustonteista (allekirjoitettu 1.7.2026) · Liperin kunta · Land deal

Operator

Plan

Välikankaan teollisuusalue · Block: 220, 223

Liperi — All data and other projects in this municipality

Project data: Datakeskushankkeiden kansallinen rekisteri (datakeskusrekisteri.vercel.app), CC BY 4.0. Modified: combined with municipal decisions. Retrieved .